Maldives Transport & Contracting Company (MTCC) says that 77 percent of the Land Reclamation and Shore Protection of Th. Hirilandhoo has been carried out
Project Update: Land Reclamation and Shore Protection of Th. Hirilandhoo
— MTCC Plc (@MTCCPlc) October 5, 2025
Revetment operations are currently ongoing. Overall project progress is 77%
Follow more updates at: https://t.co/SfVAzkW2pp #MTCCProjects #TeamMTCC #RayyithungeKunfuni #GaumuBinaakurumugaaMTCC pic.twitter.com/0E2qh86FFE